Start Date: March 1, 2022

Completion Date: December 2024

Ebenezer Sewer Basin Improvements will increase sewer capacity in the Ebenezer Basin. First Utility District’s contractor will be building a new sewer pump station at Little Creek Lane, a new sewer pump station and equalization basin at 1840 Ebenezer Road, and installing pressurized sewer mains along Northshore Drive, Northshore Hills Blvd, Norlake Circle, and Ebenezer Road. Expect lane closures on these roads as well as crossings of Whittington Creek Boulevard and Cottington Court. Vehicular access will be maintained at all times. Most of the off-site work along roads is expected to take place summer and fall of 2023. Pump station work will continue until summer of 2024. Incidental work may require pavement repair, re-seeding yards, and trimming or removal of vegetation or landscaping in right-of-way and existing utility easements.

We recognize this work is an inconvenience in your neighborhoods. Please contact FUD Engineering with specific concerns, and we are happy to work with you toward resolution.